Timing Analysis of Paths Part - I

Today, we are going to see the computation of delay of a path. Also, we will discuss some question arises during the computation. Here, we go………………

 

We are going to perform the analysis of a path e.g. Reg-to-Reg path. We are discussing the setup and hold analysis of the given timing path. Also, we answer the question of -

  • why we used max and min delay of the cell? 
  • why we considered the Min delay and Max delay table for hold and setup analysis respectively?
  • why we are not considered the worst case and best case in the same analysis?

As we have seen in the previous post, the delay of a cell is depending on input slew (transition) and output load. Here, we are discussing delay calculation of path by just directly providing min and max delay. In the actual project, these delay table provided in a standard format called Liberty by the process of Characterisation. The Liberty file is providing by library vendor (it can be Fab also).

We will discuss the Characterisation and Liberty file under the heading of Design setup.

For the analysis, consider the following values,

Min Combo logic delay: 0.2ns   Max Combo logic delay: 0.7ns

Min Clk-to-Q delay: 0.4ns   Max Clk-to-Q delay: 0.7ns

Setup time of FF: 0.3ns   

Hold time of FF: 0.3 ns

Time period: 2ns

 

Figure: Reg-to-Reg Path
Figure: Reg-to-Reg Path

While performing setup and hold analysis we have used Min delay table for Hold analysis and Max delay table for Setup analysis.

Why So??

A chip must work in all possible conditions whether is a normal case, best case or even in the worst case. While analysing a timing path, we always perform the analysis in the worst case. Because if design meets its all timing constraints in the worst case, then it will work in any condition or any case.

Now, while performing the setup analysis, we check whether data is stable or not during setup time. It means that data must be calculated or processed before reached to setup time phase. Here if the Flip Flop does not have enough time to process the data the flip flop reached into metastability state.  This is only happening when data is slow and it causes setup violation. This case occurred when at worst PVT corner. Means slow process, low voltage and high temperature. That’s why while performing setup analysis, we used Max Delay Tables.

Similarly, while performing the hold analysis, we check whether data is able to capture by flip flop or not. While doing so, data must not be changed for hold time interval i.e. data must be stable. If data change during a hold time interval, the flip flop reached into metastability state and caused hold violation. This is only happening when data is faster. This case occurred when at best PVT corner. Means fast process, high voltage and low temperature. That’s why while performing hold analysis, we used Min Delay Tables.

In short, slower the data caused setup analysis and faster the data caused hold violation.

If we see as per the formula of setup and hold analysis, then the picture is different. To consider the worst-case:

In Setup Analysis: For AT, we can use Max Delay Table; For RT, we can use Min Delay Table.

In Hold Analysis: For AT, we can use Min Delay Table; For RT, we can use Max Delay Table.

But we can not use two different PVT corner at the same analysis. Also, it is not efficient. That’s why we have to consider only max delay table for setup analysis and only min delay table for hold analysis.  

 

REG-TO-REG PATH ANALYSIS

Now, we can move towards timing analysis of Reg-to-Reg path. Considers the values and refers to the above diagram for the analysis.

The analysis consists of Arrival Time (AT), Required Time (RT), Setup Time and Hold Time. What are AT and RT? For it, refer the previous post of TERMINOLOGIES OF STA.

Setup Analysis

AT = (Clk-to-Q delay)MAX + (Combo delay)MAX

AT = 0.7 + 0.7

AT = 1.4 ns

RT = Time period   - Setup time of FF

RT = 2  – 0.3

RT = 1.7 ns

Setup Analysis = RT – AT = 1.7 – 1.4 = 0.3ns (MET)

 

Setup Analysis
Figure: Setup Analysis

Hold Analysis

AT = (Clk-to-Q delay)MIN + (Combo delay)MIN

AT = 0.4 + 0.2

AT = 0.6 ns

RT =  Hold time of FF

RT = 0.3ns

Hold Analysis = AT – RT = 0.6 – 0.3 = 0.3ns (MET)

 

Hold Analysis
Figure: Hold Analysis

Here, the values of delay are random and path also met. But in actual analysis, it varies.

There are some other paths which we have to analyses such as reg-to-out and in-to-reg. In these paths, the component like input external delay and output external delay is added. We will see such path analysis in post.

 

 

At this note of discussion, we stopped here and we will continue this topic in the TimingAnalysis of Paths Part - II. Thank You. Have a nice day.


Comments

Popular Posts